Importing a lift into Algeria: steps and costs

Real lead times, customs classification, taxes, shipping costs: the full process of an import operation.

Container carrier at the quayside under the gantry cranes of a port terminal

Local products are often limited to assembling imported parts and craft-made components, with a lack of transparency on the origin of the components. Importing remains the most accessible route to obtain a unit that is 100 % compliant with European standards.

Who can import, and what

Building professionals, property developers, manufacturers, or anyone holding a trade register can import a lift — like a goods lift or similar equipment — for their needs or as part of their projects.

The operation is subject to rules requiring proof of the product’s origin and compliance. A complete lift cannot be imported if it does not meet the European standards in force, at a minimum EN 81-20. Importing components and spare parts intended for local manufacture remains possible, with the risk of not meeting international safety standards.

When to launch the operation

Foreign manufacturers rarely keep lifts in stock: dimensions, finishes and number of levels make each unit one of a kind. On an already built building, starting early allows configuring to the millimetre. On a building under construction, the unit is installed at a certain stage — but the structural work must scrupulously follow the specifications ordered, otherwise the lift may be impossible to install.

  • Manufacturing: 6 to 8 weeks.
  • Delivery: 1 to 4 weeks — about 48 h from France, much longer from Turkey or China.
  • Average total: about 12 weeks, excluding installation time.

The import steps

You can go through a specialised company or run the operation yourself to reduce the final cost and control the product’s origin. In the latter case:

  • selecting the foreign supplier;
  • obtain a proforma in foreign currency;
  • domiciling the proforma with your bank;
  • appoint a freight forwarder for customs formalities.

Get in touch early with the three parties to the operation: the supplier, the bank and the freight forwarder. It is over the course of these steps that you must verify the equipment’s compliance, by requiring a certificate of origin and a certificate of conformity. The customs tariff position for lifts and goods lifts is 8428101900.

Costs to plan for

  • the cost of equipment and transport, both dependent on the exchange rate applied at payment;
  • bank charges — significantly higher in private banks than in state banks;
  • customs duties;
  • the charges at the port of unloading;
  • the freight forwarder’s service.

Customs duties consist of VAT (19 %), the solidarity tax (2 %) and the tax linked to the tariff position of lifts (5 %). European products are exempt from the latter, unlike those from Asia and Turkey.

Shipping costs, handled by the freight forwarder, cover the exchange of documents with the shipping line, unloading the container, handling, storage and container fees depending on the free time granted. The amount depends on the mode of transport, the place of unloading and the duration of the procedure.

In summary

Importing remains financially advantageous, but complex for a novice. It is better to be advised by a specialised company on the technical side and on the availability of spare parts. We regularly support clients who import their own units, via our French partner Eurolift Ascenseurs.

On video

Play the video: Sodimas, the leading French lift manufacturer
Sodimas, the leading French lift manufacturer

A lift or goods lift project?

Let’s talk. Our teams reply within 48 hours with a first estimate.